TURN-AROUND TIME FOR BUILDING PERMIT ISSUANCE

IN WASHINGTON STATE

(MRSC Email Survey – October 2001)

City or County

Population

(1999 est.)

Minor

Permits

Residential Permits

Commercial

Permits

Remarks (all times in this table are working days/weeks)

A number of respondents pointed out that times shown for their jurisdiction are for completed applications and do not include time for providing additional information or clarifications or for correction of errors. Also, times shown do not include zone changes, conditional use permits and other land use actions. Several respondents pointed out the statutory 120-day processing requirement of RCW 36.70B and that time required for the applicant to make corrections or supply additional information is not included in the 120 days. See the Comments section of this survey report.

Adams Co.

N/A

 

2 Weeks

 

If plans are in order & other permits obtained, then 2 days.

Bainbridge Island

19,840

 

5 Weeks

   

Bremerton

36,270

     

8 weeks is current average, but want to reduce to 4 weeks with more staff.

Brewster

2,065

 

1-2 Weeks

 

More complex projects: 3-4 weeks.

Bridgeport

2,125

 

1-2 Weeks

 

More complex projects: 3-4 weeks.

Burien

29,770

 

4-6 Weeks

8-10 Weeks

Permit application review timelines available as information handout.

Clark Co.

N/A

7-14 Days

14-21 Days

30 Days

Comm. tenant impr. 30 days. All times average. See comments for table.

Colville

4,750

1-2 Days

1-2 Weeks

2 Weeks

 

Cowlitz Co.

N/A

 

1-2 Weeks

3 Weeks

See comments.

CTED & Shockey

N/A

     

See comments.

Duvall

4,435

 

2-4 Weeks

 

See comments

East Wenatchee

5,395

 

2-3 Weeks

6-8 Weeks

Light Comm. is same as Res.

Issaquah

10,130

     

See comments.

Jefferson Co.

N/A

     

Average is 34 days. Range is 1-147 days.

Kalama

1,630

 

2 Weeks

 

Critical area issues could add another 2-3 weeks.

Kenmore

17,168

2-3 Weeks

2-3 Weeks

2-3 Months

After planning permits are obtained. Commercial tenant improve.: 3-4 weeks.

Lacey

29,020

     

See comments.

Lynden

8,910

 

7-10 Days

14-21 Days

 

Mercer Island

21570

30 Days

60 Days

60 Days

See comments.

Mill Creek

11,110

 

2-3 Weeks

3-6 Weeks

 

Mukilteo

17,180

 

4 Weeks

6-8 Weeks

See comments for extensive discussion.

Newcastle

8,605

     

Goal for all permits is 4-6 weeks.

Nooksack

890

 

1Week

3-4 Weeks

See comments.

Okanogan Co.

N/A

 

2 Weeks

 

Average time, after planning department review.

Pateros

630

 

1-2 Weeks

 

More complex projects: 3-4 weeks.

Pierce Co.

N/A

 

14-21 Days

60-80 Days

Assuming no surface water or ESA reviews.

Pullman

24,540

3 Weeks

 

Quinault Nation

N/A

     

2 days for most permits, 2-4 weeks for larger projects.

Richland

36,880

 

12 Days

20 Days

2nd Reviews are 12 days for Comm., 9 days for Res. Tenant Imp. are same as Res.

Seattle

540,500

     

120 days. See comments.

Shoreline

52,030

     

See comments.

Skagit Co.

N/A

     

29 days is median. See comments.

Snohomish

8,250

 

1 Month

8 Weeks

Multi-family: 6 weeks.

Snoqualmie

1,980

 

2 Weeks

3-4 Weeks

 

Spokane Co.

N/A

1 Day

3 Days

34 Days

 

Stevens Co.

N/A

 

7-10 days

 

See comments.

Sumas

976

 

1 Week

1 Month

See comments.

Sumner

8,495

 

2 Weeks

4 Weeks

 

Tacoma

187,200

 

2 Weeks

8 Weeks

 

Thurston Co.

N/A

 

10 Days

 

Average time.

Walla Walla Co.

N/A

     

12-14 days in unincorporated county area.

West Richland

7,625

2-3 Days

3-4 Days

5-9 Days

 

Whatcom Co.

N/A

 

1 Month

 

In busy season, may be 6-7 weeks.

Whitman Co.

N/A

 

1 Week

2 Weeks

 

Winthrop

380

     

30 days, average

Yakima

65,500

3 Weeks

Less time in Winter, more in Summer